BUSI 313 Quiz 2
BUSI 313 Quiz 2 Liberty University
Set 1
- If the project time should be accepted, then the project must be completed on time.
- The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called
- One way for a project manager to communicate the authority granted to individual project members is to publish a
- A communication plan is a key component for giving guidelines on how to track project
- Which of the following is NOT true regarding scope creep?
- The highest element in the hierarchical breakdown of the WBS is the first major deliverable for the project and the lowest element is a work package.
- “Reviews with customer” only refers to projects with external customers who are paying for the project.
- There is a strong correlation between project success and clear project scope definition.
- Which of the following is least likely to be included in a work package?
- Which of the following does NOT help describe a bottom-up estimating approach?
- The salary of the project manager would be an example of what type of cost found in a project?
- Which of the following is a good condition for top-down estimating?
- Organization culture can significantly influence project time and cost estimates.
- Which of the following would best represent direct project costs?
- Refining estimates may be necessary for a number of reasons. For example, design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are good examples of
- The salary of the project manager and her administrative assistant is classified as direct labor costs.
- An external view of a Mega Project based upon the outcome of similar projects undertaken in the past is known as:
- Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
- A sequence of connected, dependent activities is termed a(n)
- When translated into a project network, a work package will become
- Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
- Which of the following represents an activity on an activity-on-node (AON) project network?
- Activities which can take place at the same time are termed
- An activity is an element of the project that always requires time.
- The likelihood the original critical path(s) will change once the project is initiated is referred to as
Set 2
- Creating a communication plan typically follows a process that begins with a stakeholder analysis.
- If the project time should be accepted, then the project must be completed on time.
- All of the following are usually included in a work package EXCEPT
- The final stage in defining a project is coding the organization breakdown structure or OBS for the information system.
- The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called
- The _________ is used to assist in making project trade- offs among schedule, budget, and performance objectives.
- In reviewing the project plan, Susan sees that the first prototype must be completed by October 12. This would be best classified as a
- For large companies, the organization breakdown structure is used rather than the work breakdown structure.
- If a project criterion should be optimized if at all possible, it is classified as being constrained.
- Which of the following is NOT true in regard to the level of detail estimates should contain?
- The consensus method of estimating costs is a bottom- up technique.
- The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.
- Benefits of Reference Class Forecasting include
- While it may be true that Mega Projects are by nature extremely difficult to estimate, another factor identified in the consistent pattern of estimating difficulties is:
- Large projects that have long time horizons and a very high complexity can be referred to as
- An external view of a Mega Project based upon the outcome of similar projects undertaken in the past is known as:
- The salary of the project manager would be an example of what type of cost found in a project?
- Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of
- The forward pass in project network calculations determines all of the following EXCEPT
- Which of the following can be used without coordinating with managers of succeeding activities?
- Arrows on an activity-on-node (AON) project network represent
- When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
- Information to develop a project network is collected from the
- A(n) _________ activity has more than one dependency arrow flowing from it.
- When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select