MGMT 625 Quiz 2
MGMT 625 Quiz 2
- The ___________________ usually represents activities that have zero float/slack.
- Individuals that the organization employs to perform tasks for the operation and/or projects are referred to as
- Quality assurance, design engineering, shipping and receiving, and legal advisory are all examples of:
- WBS is
- The amount of time an activity’s start can be delayed without affecting the overall project is
- refers to the overall number of resources required for a work activity within a specified time.
- The activity information checklist should include the following information
- What two ways does a project manager have to design extra time on a project for particular work activities that may require special attention?
- All resources present two main constraints to a project:
- A compilation of completed work activities to form a final product identified by the customer as accomplishing an objective
- This estimating process allows the use of both optimistic and pessimistic values to calculate an expected duration.
- Resources acquired by the organization used to carry out the activities of business and accomplish the strategic objectives of the organization are
- Indirect project resources might be used during the course of project work activities but are not allocated to particular work package activity.
- Activity organization has to be designed at two levels:
- What are the four activity relationships based on activity dependency?
- Activity definition is the most critical phase of the project life cycle because
- In most cases, work authorization and spending are the responsibility of
- When a risk with a high probability or high impact to the project is identified, extra time should be calculated into the activity to compensate. This is called:
- Program resource estimating is used mainly in high level organizations
- What are the elements of the triple constraint?
- Which is not one of the primary components for information gathering?
- Two processes are used to evaluate work activities for diagramming a network:
- Authorization for scheduling falls under two general categories:
- The _______________ relationship simply establishes one or more activities that need to be completed before the next activities connected in the network.
- When using the Activity-on-Node diagram, activities can be used multiple times within the diagram